The Alabama Department of Environmental Management (“ADEM”) and Evonik Corporation (“EC”) entered into a May 8th Consent Order (“CO”) addressing an alleged violation of an air permit. See Consent Order No. 24-XXX-CAP.
The CO provides that EC operates a chemical manufacturing plant in Mobile County, Alabama.
The facility is stated to have been issued a Major Source Operating Permit (“Permit”). Further, identified in the Permit is what is described as a Rohacell Production Unit denominated Emission Unit 4.3.
The plant is stated to currently operate under a Permit Application Shield.
ADEM is stated to have received a Notification of Permit Deviation on August 31, 2023, from EC concerning Permit Proviso #2 of the Emission Monitoring Section of Emission unit 4.3. The Notification of Permit Deviation is stated that EC failed to monitor and record the pressure drop across baghouses 402 and 407 for a total of 41 days.
EV neither admits nor denies ADEM’s contentions.
A civil penalty of $28,500.00 is assessed.
A copy of the CO can be downloaded here.
The Between the Lines blog is made available by Mitchell, Williams, Selig, Gates & Woodyard, P.L.L.C. and the law firm publisher. The blog site is for educational purposes only, as well as to give general information and a general understanding of the law. This blog is not intended to provide specific legal advice. Use of this blog site does not create an attorney client relationship between you and Mitchell Williams or the blog site publisher. The Between the Lines blog site should not be used as a substitute for legal advice from a licensed professional attorney in your state.